Tribe Hotel, Perth: How 63 Factory-Built Modules Were Stacked into a Hotel

Design: IDLE Architecture Studio | Project: Tribe Hotel Perth | Location: Perth, Australia | Project team: Salta Properties (client), MP Modular (modular supplier), Bonacci Group (structure), Wood & Grieve Engineers (services), Probuild (builder), Travis Walton (interior design) | Photography: Earl Carter, published with bowerbird

Tribe Perth is a hotel of 63 container modules, designed by IDLE Architecture Studio for Salta Properties. Each module holds two hotel rooms and a central corridor, and the modules were manufactured off site, transported and stacked over a number of levels.

IDLE says the modules were assembled on site in just 14 days, reducing construction cost and site waste, and the hotel opened in June 2017.

Brief and process – Why modular for a hotel?

The Tribe team approached IDLE because of its earlier work in modular architecture and its experience in the hotel and residential sector. Both parties saw the social, financial and logistical challenges facing the industry and agreed that a modular process offered streamlined construction and a high-quality finish.

IDLE and Tribe worked together to refine an efficient, design-focused module that could be made off site in a controlled environment, transported and stacked.

The module – What is inside each unit?

Each module has two compact hotel rooms and a central corridor. The rooms are carefully detailed and furnished, with a fully glazed wall that gives wide views of the inner-city context.

Site assembly – What happened once the modules arrived?

IDLE describes the sequence after delivery:

  • Stacking. The 63 modules were assembled on site in 14 days.
  • Services. Services were integrated once the modules were in place.
  • Shrouds and screens. Shrouds were unfolded and prefabricated facade screens were installed.
  • Finish. Landscaping was completed and the doors opened in June 2017.
Facade section drawing, annotated with the module structure, glazing, sun shrouds and module connection

Facade – How does the building hide its modular roots?

IDLE says new technologies and materials in the facade give a striking, cutting-edge result that belies its modular origins and stands as a symbol of Tribe’s entry into the Australian hotel market.

Public spaces – What is at ground level?

Ground-level spaces include the main entry, a foyer and a courtyard.

What it shows about modular hotels

  • Develop the module with the operator. IDLE and Tribe refined one efficient, design-focused module.
  • Stack fast. 63 modules were assembled in 14 days.
  • Prefabricate the skin too. Facade screens were installed as prefabricated elements.
  • Make the stack disappear. The finished facade belies the modular structure.

Photography by Earl Carter, published with bowerbird.